As part of our commitment to keeping clients informed and supply chains resilient, our procurement team has compiled this report of global component market conditions. Rising raw material costs, AI-driven demand, and ongoing geopolitical developments continue to reshape lead times and pricing across key product groups.

Analog

High-End:

Prices increase due to rising raw material and transport costs. There is an upward trend in lead times caused by increasing demand.

Commodities:

Prices increase due to rising raw material and transport costs. Higher demand keeps lead times increasing. It is recommended to place long-term orders to secure supply.

Discretes

Lead times are increasing rapidly. It is highly recommended to place long-term orders to secure supply. Prices increase due to rising raw material and transport costs.

Recent events at Nexperia, including export restrictions and governance-related actions, have heavily impacted the supply chain, lead times remain high

 

 

 

 

 

 

 

 

 

 

 

Memory

ALL PRICE TENDENCIES ARE INDICATED IN USD

Please provide long-term demand across all technologies. Forecast/Order backlog is key for planning demand properly.

General situation:

The allocation situation dramatic on DRAM and NAND products. Massive price increases on the latest technologies. AI demand remains robust and is impacting memory availability globally.

DRAM: Massive price and lead time increases – especially high impact on LPDDR4/DDR4 and newer technologies like DDR5/LPDDR5 but also legacy technologies such as DDR3. Unplanned upside for CY2026 impossible to supply, please check backlog. Long-term orders needed more than ever to secure supply for CY2027.

NAND Flash: eMMC on allocation. No supply available for upside business. SSD supply impacted by data center demand.

NOR Flash: Increasing prices and lead times.

SRAM: Stable availability – minor constraints on specific technologies.

 

Opto

LEDs: Overall good supply situation.

Vishay: Lead time 4-20 weeks for majority of the Optocoupler portfolio.

Samsung: Official announcement of LED-business exit.

 

 

 

 

 

MCU & DSP

Program. Logic

Logic

Lead times are increasing rapidly. It is highly recommended to place long-term orders to secure supply. Prices increase due to rising raw material and transport costs. Recent developments at Nexperia, such as export restrictions, governance-related measures, and internal operational challenges, continue to affect the supply chain.